Not when the contract says. Chapter 28 gives the owner a fixed period and the contractor above you a short one after that, and the total is the date you can point at.
The pay application or invoice going up the chain. Everything counts from here.
Optional. If you know it, the pass-through counts from that day instead, and it usually lands earlier.
Enter the day the payment request went in
The owner has 35 days. The contractor above you has 7 more after that. Nothing is dated until you give the page the day it all started from.
Prompt payment is when the money was due. The lien affidavit is what you do when it never came. Somebody who only knows the second date spends two months feeling unreasonable for asking.
A chase that names the statute and the day is a different conversation from one that asks whether there is any news on the payment. Same money, same relationship, one of them gets answered.
Worked example
The payment request reached the owner on 2026-08-01, and you are a sub below the contractor, so your money runs the owner period plus the pass-through.
Sep 5, 2026
This is the day the money was legally due, not the day it is polite to ask. Past it, the unpaid balance is overdue under chapter 28 whatever the contract says about net 60.
Counted as 35 days from the payment request (2026-08-01).
Tex. Prop. Code s.28.002(a)
Sep 12, 2026
Counted the whole way down: the owner pays the contractor, and the contractor then has the pass-through period to pay you. Nobody publishes this total, and it is the only date a subcontractor actually needs.
Counted as 35 days to the contractor, then 7 days down to you, from the payment request (2026-08-01).
Tex. Prop. Code s.28.002(a) and s.28.002(b)
Send the invoice from the platform and the statutory dates land on it: when the money is due, when it went past due, and what the next step is. You stop working out which invoice is late by scrolling a bank feed.
The chase then goes out on the day it is due rather than the week you remembered, and the record of when you asked is already written.
prompt_payment_owner_days (US-TX) Published source Last read from the source Aug 12, 2026.prompt_payment_passthrough_days (US-TX) Published source Last read from the source Aug 12, 2026.Texas lien deadline calculator
The 15th-of-the-month arithmetic, done. Monthly fund-trapping notices and the affidavit deadline, commercial or residential.
Markup and margin calculator
The arithmetic solo contractors lose money on. 20% markup is not a 20% margin, and this shows you the gap in dollars.
Contractor hourly rate calculator
What you have to charge, worked backwards from the year you want. Counts the hours you work against the hours you actually invoice.
Ontario lien deadline calculator
Preservation, perfection and the annual holdback cycle, counted with the periods in the Construction Act.