There is nothing to lien on a bonded job, so the notices are the claim. One of them has a floor as well as a deadline, and serving it early is the same as not serving it.
The day you started work or made the first delivery. This starts the notice to contractor and the floor on the notice of nonpayment.
The last day of your original scope. Warranty work and going back to fix something do not count.
Enter the days you were on the job
Two dates run this whole page: the first day you furnished and the last. Everything else is counted from them.
The notice of nonpayment has a floor. A claimant who fires it off the week the payment is missed has filed a document with no effect, and nothing tells them so until the surety does.
You are entitled to it, and it names the surety you have to serve. Asking for it on day one costs a phone call. Asking for it on day 85 is how a claim expires inside the window it was meant to be served in.
Worked example
First day Jun 22, 2026, last day Aug 16, 2026, working below the contractor who furnished the bond, which is the position that owes both notices.
Aug 6, 2026
Miss it and the bond is closed to you before the job is even finished. It is served before you are owed anything, which is exactly why it gets forgotten.
Counted as 45 days from the day you began furnishing (2026-06-22).
Fla. Stat. s.255.05(2) and s.713.23(1)(b)
Aug 6, 2026
The only floor in the whole chain. Serve it earlier and you have served nothing, and the claimant who did it usually believes they are covered right up until the surety says otherwise.
Counted as 45 days from the day you began furnishing (2026-06-22).
Fla. Stat. s.255.05(2)(a)2
Nov 14, 2026
The hard end of your claim on the bond. Counted from the last day you furnished, and warranty or corrective work does not restart it.
Counted as 90 days from the last day you furnished (2026-08-16).
Fla. Stat. s.255.05(2)(a)2 and s.713.23(1)(d)
Aug 16, 2027
Serving both notices keeps the claim alive. It does not collect the money. The action itself has its own deadline and it is the last one.
Counted as 12 months from the last day you furnished (2026-08-16).
Fla. Stat. s.255.05(10) and s.713.23(1)(e)
Set the job up as bonded and the notice window sits on it from the first day you furnish, with the surety and the bond number on the record. The date arrives at you instead of you going looking for it in the week it closes.
The invoices, the delivery dates and the last day you were on site are already in one place, which is the evidence the notice depends on anyway.
bond_notice_to_contractor_days (US-FL) Published source Last read from the source Aug 12, 2026.bond_nonpayment_floor_days (US-FL) Published source Last read from the source Aug 12, 2026.bond_nonpayment_ceiling_days (US-FL) Published source Last read from the source Aug 12, 2026.lien_foreclosure_months (US-FL) Published source Last read from the source Aug 12, 2026.Florida lien deadline calculator
The 45-day Notice to Owner, the 90-day Claim of Lien and the one year to enforce it, dated from your first and last day on the job.
Markup and margin calculator
The arithmetic solo contractors lose money on. 20% markup is not a 20% margin, and this shows you the gap in dollars.
Contractor hourly rate calculator
What you have to charge, worked backwards from the year you want. Counts the hours you work against the hours you actually invoice.
Ontario lien deadline calculator
Preservation, perfection and the annual holdback cycle, counted with the periods in the Construction Act.