civ_pioneer9210d

Soil-cement column grid collides with fibre duct during widening – chevron or shallow columns?

Eight-hundred-millimetre soil-cement columns on one-metre centres reinforce a widening near a live fibre duct sitting 0.9 m off drawing. The city wants zero outage risk. Options: chevron grid, shallow columns over the duct, or hand-placed flowable fill. If you swerved mid-grid, how did you keep geotech, utility, and scheduler all smiling?
4

Comments (13)

FA
fatima.cities9 days ago
Press release trumpeted uninterrupted fibre for 3 000 homes, spinning an engineering pivot as a community win.
PA
parker.jungle9 days ago
Spray-paint the chevron grid so crews place columns without late-night tape measure confusion.
BE
benji_ee9 days ago
Satellite SMS numbers on site; cell drops inside the cut walls can delay safety calls.
DE
deeptank.pm9 days ago
Keep binder at fourteen percent in the top metre; clay up there still needs chemistry.
SI
sitaspecs9 days ago
Cost plus five percent, schedule minus ten days compared with relocating the duct. Logged as classic value-engineering.
JO
joe.bridges10 days ago
Night drilling means binder cools; raise silo temperature in the method statement or viscosity spikes.
ZO
zoe.assetlife10 days ago
Install an access pit now; future splice ease beats later digging.
FR
francesca.struct10 days ago
Eight vibrating-wire gauges on the duct fed live microstrain to the utility’s SCADA; peace of mind in one graph.
HP
hp.consulting10 days ago
Insurance rider disappeared once the grid moved clear of the duct; underwriter feared a fibre hit.
TE
tendai_supplychain10 days ago
Binder order dropped fifteen tonnes after the chevron tweak; one phone call cancelled an extra silo rental.
AN
angie_structural10 days ago
Column depth over the gas line shrank from 8 m to 4 m; we thickened the slab 60 mm with mesh to compensate.
MK
mkale.codes10 days ago
A Plaxis parametric bowl made the utility engineer approve in one meeting; visuals beat tables.
TE
terra.solid10 days ago
Chevron grid at 1.3 m centres in a V around the duct held settlement under 5 mm. Topped with a 200 mm rich-asphalt strip for stiffness correction.