We use cookies to keep you signed in and to see what's working and what breaks. No advertising cookies, nothing sold. Details in our Cookie Policy.

FloridaUpdated 20 August 202616 minute read

Try this on a real business

Open a seeded business in your trade. Nine jobs on the pipeline, a quote sent and viewed, a deposit paid, and an invoice already overdue.

Open the demo business

No card, no form. Sign in later and everything you built stays on the same account.

The last 8th Edition permit application in Florida goes in on December 30, not 31

You quoted a Broward fit-out in October for a February start. Your engineer drew the set in November. The client took his time, signed on December 18, and the office was shut for the week after that, so the permit application walked up to the counter on January 6. Nobody was in a hurry about a job that did not break ground for six weeks.

That application landed on the wrong side of one date. Applications submitted on or after December 31, 2026 are reviewed against the 9th Edition of the Florida Building Code. Applications accepted before that date stay on the 8th Edition for the life of the permit. So a set drawn in November to the edition your designer had been working to all year is now being read against a different one. The correction letter comes back, the engineer revises at $6,400, and the job goes to the back of a review queue it had already sat in once. Start slides from February 2 to mid March. Six weeks of supervision and general conditions carried on a fixed price at $2,900 a week is $17,400. On a $410,000 contract you priced to hold 12 percent, that is $49,200 of margin with $23,800 taken out of it, and all of it came out of a filing date that was seven days later than it needed to be.

By the end of this page you will have a permit application date written next to every Florida job in your pipeline, chosen rather than inherited. You will have your live quotes sorted by which edition will actually review them, the edition named in writing in the design brief before the next sheet is drawn, the two credentials that decide whether a counter will even accept your application confirmed current, and the last working days of December booked as a filing window instead of left as a hope. The date comes from the Florida Building Commission's own 2026 workplan. The rule underneath it is section 553.73 of the 2025 Florida Statutes, quoted below.

Read the Florida Building Code switchover as a date on your application, not on your calendar

Five dates hang around a Florida job and only one of them decides the code edition.

The date you might be thinking ofWhat it decides about the code edition
Contract signatureNothing
Permit application, accepted by the building departmentThe edition, for the life of that permit
Permit issueNothing
First day of work on siteNothing
Final inspectionNothing

That is the whole mechanism, and it is unusually clean for a construction rule. A job whose application is accepted in December is an 8th Edition job through every inspection that follows, however long the build runs. A job whose application goes in the following week is a 9th Edition job from its first sheet.

Section 553.73(7)(a) puts the Commission on a three year cycle, and 553.73(7)(e) sets the earliest date a new edition may bite:

"A rule updating the Florida Building Code in accordance with this subsection shall take effect no sooner than 6 months after publication of the updated code."

s.553.73(7)(e), 2025 Florida Statutes

Read the words rather than the summary. No sooner than is a floor, not an offset. The 9th Edition was posted online on December 22, 2025, which made roughly June 22, 2026 the earliest date it could lawfully have taken effect. The Commission did not take the earliest date. It took the traditional triennial one, December 31, and that is the date its own workplan carries. Twelve months rather than six, and the six month line in the statute never promised otherwise. If you have heard someone say the code was going live last summer, that is where they got it, and they were reading a floor as a schedule.

Now the part that costs a job. On or after December 31 means December 31 is already the 9th Edition. The last day an application can go in under the 8th is Wednesday December 30, 2026. Read that twice, because "by the end of the year" is how people will remember it, and the end of the year is one day too late.

The calendar around it is tight. Christmas Day 2026 falls on a Friday. That leaves Monday 28, Tuesday 29 and Wednesday December 30 as the working days between the holiday and the wall, and those are three days when building department counters run short handed and intake runs behind.

And the operative word in the rule is accepted, not submitted. An application handed back at intake for a missing page, an unsigned affidavit, a Notice of Commencement not yet recorded or a fee not yet paid is not an accepted application. It is a stack of paper you are still holding on December 31. Filing on the 30th gives you nothing to fix with. Filing on the 15th gives you two weeks.

Sort every live quote by which side of December 30 its permit lands on

You do not need to know a single technical difference between the two editions to know what this does to your price. A price is built on a requirement set, and a requirement set your estimator did not read is a number your estimator did not put in. The application date is the one variable in a fourth quarter Florida quote that you can pin for free. File before December 30 and the requirement set your designer worked to is the requirement set the plan reviewer reads. File after and you have priced against one document and will be built against another.

So take the pipeline and do one sort, this week, before the holidays eat the time.

Where the job is nowWhere the application landsReviewed underThe move
Signed, set complete, ready to fileOn or before 30 Dec8th EditionFile it. Do not wait for the deposit to clear
Signed, design still runningJanuary or later9th EditionTell the designer this week
Quoted, acceptance window still openClient's choice, not yoursUnknownName the edition on the quote
Quoted for a spring startFebruary to April9th EditionPrice it there and say so
Won a bid, no design startedJanuary or later9th EditionBrief the designer to the 9th from sheet one

The acceptance window is the one that gets missed. A quote issued on December 10 with a standard 30 day acceptance can be signed on January 9. Your price was built on one side of the line and the job will be built on the other, and nothing about that quote said so.

There are two ways out and only one of them is any good. You can shorten the acceptance window on anything you quote in the fourth quarter so that signature and filing land on the same side of the date. That works, and it also reads as pressure to a client who does not know why you are suddenly in a rush. Better is to write the assumption into the quote: this price assumes a permit application accepted on or before December 30, 2026 under the 8th Edition of the Florida Building Code, and an application accepted after that date is reviewed under the 9th Edition and re-priced. That is a fact about the job, not a squeeze, and it converts a silent risk into a line the client reads and initials. It is also the sentence that lets you hold your number in February without an argument.

Tell the designer which edition to draw to before the next sheet

The plan set is what gets rejected, and the plan set is drawn months before anyone carries it to a counter. Somebody on your team is making an edition assumption right now, in silence, on your behalf.

Put it in the design brief in writing and put the assumed application date next to it. Two sentences: this set is drawn to the 8th Edition of the Florida Building Code, on the basis that the permit application will be accepted on or before December 30, 2026. If that date moves, the set is redrawn to the 9th before it is submitted.

The expensive version of this is not incompetence, it is drift. A set is started in October on one assumption. The client signs three weeks later than anyone expected. A subcontractor's shop drawings hold up a coordination review. The filing date quietly moves into January and the drawings do not know, because a drawing has no way of finding out. So the fix is a person, not a note: when the filing date moves, the designer hears about it the same week, and hears it as a decision rather than as news.

If the application is landing in 2027, draw to the 9th from the first sheet. A set drawn to one edition and patched toward another after a correction letter is two rounds of engineering fees and a second trip through a review queue, and it arrives at the same place the direct route would have reached for less money and six weeks earlier.

Check the two credentials that decide whether you can file in December at all

The code edition is not what stops most December filings. Two credentials do, and both of them went stale earlier in the same year while you were busy.

The certified license renewed on August 31, 2026. DBPR and CILB certified licenses run on a biennial cycle ending August 31 of even numbered years, with 14 hours of continuing education per biennium. That CE is not one lump you can buy on a Sunday. The rule sets minimums of one hour each in workplace safety, workers compensation, business practices, the advanced Florida Building Code module, and laws and rules. Add an hour of wind mitigation if you hold General, Building, Residential, Roofing, Specialty Structure or Glass and Glazing. Add an hour of pool electrical for the pool and spa categories, and an hour of cementitious cladding and stucco for General, Building, Residential and Specialty Structure. A first renewal runs on its own arithmetic, and it runs the opposite way to how most people guess it. You owe nothing at all for the year your certificate was first issued. If that certificate came more than twelve months before the biennium closed, your first renewal is 7 hours rather than 14. Come in inside that twelve months and the first renewal asks for no hours, so the newest licensees are the ones buying courses they do not owe.

Notice which module is on that list. The CE hour that exists to keep you current on the Florida Building Code is part of the same filing that keeps you able to pull a permit at all. Miss the renewal and the license goes delinquent, then null and void, and contracting on a null license is where the unlicensed contracting exposure in s.489.127 starts.

The local business tax receipt expired on September 30. Chapter 205 receipts are issued per county and per city where you operate. Renewal opens July 1 and closes September 30. From October 1 the receipt is delinquent and carries a 10 percent penalty plus 5 percent per month, capped at 25 percent. A contractor working across three jurisdictions carries three of these, and the one that has lapsed is reliably the one covering the jurisdiction the December job sits in.

Both are cheap to fix in October and expensive to discover on December 29 with a plan set under your arm.

Pull the permit early without recording the Notice of Commencement early

Here is the trap on the far side of the same move, and it catches the people who do everything else right, because it looks like being organized.

The Notice of Commencement is recorded by the owner. It is required when the direct contract exceeds $5,000, and s.713.13 wants it recorded before work actually commences, with a certified copy or a notarised statement posted at the site. It is the gate on your first inspection, and its owner, lender and surety addresses are what every later notice on the job gets served to.

It also runs its own clock, and that clock runs against you. Under s.713.13(2) a Notice of Commencement is void if work does not actually commence within 90 days after it is recorded. Record one on December 30 to keep tidy company with a permit you filed early and work has to be genuinely underway by March 30, 2027. The notice is otherwise effective for one year from recording unless a different period is stated on its face.

So the two dates come apart on purpose, and you want them apart:

InstrumentFiled whenBecause
Permit applicationDecember, as early in the month as the set allowsThe application date buys the 8th Edition for the life of the permit
Notice of CommencementWhen the job is genuinely about to startIts own 90 day clock starts at recording, not at groundbreaking

Rushing them together to feel finished is how you end up with a void notice, an inspection you cannot book, and a downstream notice stack with no addresses to serve. One carve out is worth carrying: HVAC repair or replacement of an existing system under $15,000 is exempt from the Notice of Commencement requirement under s.713.135.

Put the dates somewhere that survives the holidays

A date you decided in October and stored in your head does not make it to December 28. This is the least glamorous sentence on the page and it is the one that pays.

On AEC Stack a Florida job carries a Florida clock set rather than a generic one, and each clock carries the section that sets it and the consequence of missing it on its face rather than in a footnote somewhere. The lien and bond instruments are there: the Notice to Owner window running 45 days from first furnishing under s.713.06(2)(a), the claim of lien at 90 days from your final furnishing under s.713.08(5), the public bond notices under s.255.05. So are the administrative ones that decide whether you can trade at all: the certified license renewal, the sales and use tax return, the reemployment tax quarters, the Sunbiz annual report on May 1 with its $400 late fee that cannot be waived.

The quote is where the edition assumption belongs, because the quote is where the price was decided. Florida quotes and invoices already resolve the 12A-1.051 contract type fork and the delivery county surtax on the document, and where a fact is missing they say so and mark the total incomplete instead of quietly treating missing as zero. Write the application date assumption into the quote's assumptions with the same discipline: a quote that admits it does not yet know when it will be filed is worth more in December than a quote that guesses and stays silent.

The jobs you file in January are the ones you are bidding now, which makes the fourth quarter the point where filing dates are still cheap to choose. There are roughly 2,148 open Florida opportunities live on the platform at the moment, 1,768 of them in Miami-Dade and 380 in Orlando, refreshed weekly. A bid won in November is a December application if you set it up to be one.

What it costs

There is no monthly subscription. The platform fee is 2.5% of each invoice processed through AEC Stack, collected on payment due dates.

Everything on this page that carries a price is somebody else's charge, and the switchover itself carries none at all. It is free to be on the right side of it and expensive to be on the wrong one:

WhatWho sets itAmount or rule
Code edition, application accepted on or before 30 Dec 2026Florida Building Commission8th Edition, for the life of that permit
Code edition, application on or after 31 Dec 2026Florida Building Commission9th Edition
Permit feeYour county or city building departmentSet locally, usually on job valuation
Certified contractor license renewalDBPR and CILBBiennial, due August 31 of even numbered years, 14 hours CE per biennium
Local business tax receipt renewalEach county and city you work in, Ch.205Renewable July 1 to September 30; from October 1, 10% penalty plus 5% per month to a 25% cap
Notice of CommencementCounty clerk, recording fee set locallyRequired over a $5,000 direct contract; void if work does not commence within 90 days of recording
Sunbiz annual reportDivision of CorporationsDue May 1; $400 late fee that cannot be waived; administrative dissolution the fourth Friday of September
Construction comp exemption, per officer or memberDivision of Workers' Compensation$50, valid two years, s.440.05(8)(a)
Tangible personal property return, DR-405County property appraiserDue April 1; the $25,000 exemption goes with it if unfiled
Quote and win

On AEC Stack: the application date is a pricing decision, so the rest of the price is worth getting right in the same sitting: the sales tax inside your material line and the county surtax on top of it are in pricing Florida jobs. The instrument that has to stay out of the December rush is covered in the Notice of Commencement, and the credential the counter checks before it accepts anything is in getting your Florida contractor's license. Roofers file more permits than anyone and carry an extra CE hour for the privilege, which makes insurance funded roof work in Florida the version of this with the tightest calendar.

Take twenty minutes this week and write one extra date beside every Florida job you have open: the day its permit application will actually be accepted at a counter, not the day you hope to hand it in. Anything landing on or before Wednesday December 30 is an 8th Edition job and the only thing between you and that is filing it. Anything landing after is a 9th Edition job, and your designer needs to hear that before the next sheet is drawn rather than after the correction letter. If the honest answer for most of the pipeline is that nothing is close enough to file, that is a different problem and a more urgent one, and the Florida opportunities on find work refresh weekly.

<!-- CAPTURE LATER: a Florida job record with the permit application date entered and the assumption line visible on the linked quote, alongside the Florida clock panel showing the license renewal and Notice to Owner clocks with their statute references. Blocked in this wave: the demo tenant is Ontario. -->

Keep going

Also on pricing and estimatingMiami-Dade and Orlando permitsFilter this week's Miami-Dade County and Orlando building permits to your trade and value band, read a permit line the way an estimator does, and make a call that names the permit number.Also on pricing and estimatingGet on Florida GC bid listsA general contractor bid list is a spreadsheet on one estimator machine, and getting added is a four minute clerical act that happens the moment somebody has a complete folder on you. Here is the folder.Also on finding workFlorida bid-ready checklistThe compliance clerk emails on Tuesday for twelve documents and the bid is due Thursday. Four of them take a week to obtain. Assemble the package before you need it and every tender after that is an afternoon of work.Also on pricing and estimatingPrice a Florida jobPrice a Florida job off a cost floor that already carries the 6% state tax and the delivery county's 2026 surtax, with the $5,000 single item cap applied and a markup that produces the margin you meant to keep.Also on pricing and estimatingThe Florida handyman lineFlorida has no handyman license to get. Two tests decide whether a job is yours without one: whether it needs a permit, then whether the aggregate price clears $2,500. Plus the statute that puts painting, flooring and handyman services outside licensing entirely.Also on finding workFind Florida construction bidsFilter 2,148 live Florida contract awards, tenders and building permits down to your trade and your county in one sitting. Public records, published by the government that issued them, surfaced the week they appear.

Someone in your trade group needs this. Send it to them.

The dates that cost Florida contractors money

One email a month. The lien deadline and payment bond claim arithmetic this site already does for you, the dates it turns on, and every new guide the day it goes up.

  • Florida lien deadline calculator: The 45-day Notice to Owner, the 90-day Claim of Lien and the one year to enforce it, dated from your first and last day on the job.
  • Florida payment bond claim calculator: On a bonded job the notices are the claim. Includes the floor on the notice of nonpayment, the one deadline you can be too early for.
  • Every new guide the day it goes up. 34 are live for Florida right now, the most recent being "The Florida handyman line" on 20 August 2026.

No account. AEC Stack sends this and every email carries a one-click unsubscribe. Privacy policy.