We’re facing severe schedule compression on a 40-story mixed-use high-rise due to structural delays. Now, multiple subcontractors are working in overlapping spaces, leading to:
1️⃣ Safety risks – Increased fall hazards and material congestion.
2️⃣ Productivity loss – Crews are slowing each other down.
3️⃣ Quality concerns – Rushed work is causing rework in MEP and finishes.
The client insists on maintaining the original completion date. We’re exploring off-hours work, sequencing adjustments, and prefabrication, but conflicts persist. Has anyone successfully managed stacked trades without causing further delays?
(Construction Lawyer): Depends on what’s in the contract. If acceleration wasn’t agreed upon, forcing stacked trades could be considered constructive acceleration, and subs may be entitled to extra costs.
Some subs are already requesting change orders for inefficiencies. Would that hold up as a claim, or are they stuck with what they signed?
(Prefabrication Expert): If site congestion is killing productivity, why not move some work offsite? MEP modules, bathroom pods, even prefabricated drywall assemblies can cut down on site hours.
(General Contractor): If you can show fewer labor hours on site, subs usually come around. The key is getting prefab into their contracts early, not after work has started.
We pitched prefab, but subs pushed back, saying it restricts their flexibility. How do you get subcontractors on board?
(Safety Manager): The bigger issue is safety. I’ve seen sites where workers store materials in stairwells and corridors just to make space. It’s a nightmare for fire safety and access. If you don’t manage storage properly, trade stacking turns into a major hazard.
(Logistics Coordinator): You could set hard limits on floor storage and schedule just-in-time deliveries. Works well if trades follow it, but enforcement is a headache.
We’ve seen that, too—crew areas get overcrowded with pallets and debris. Any tips for enforcing material control without slowing things down?
(Site Superintendent): When space is tight, vertical zoning usually helps—assigning different trades to different floors and staggering progress. But some trades don’t like moving up too early because staging areas and lifts aren’t ready yet.
(MEP Coordinator): I’ve had subs refuse to move up if their material access wasn’t guaranteed. If zoning is the plan, site logistics has to be planned around it, or trades just push back.
(Construction Scheduler): The biggest mistake I see is when project teams try to solve trade stacking by cramming more people into the same schedule. If your plan is already overloaded, adding extra shifts without fixing sequencing usually makes things worse.
(Labor Productivity Specialist): If you go with shifts, make sure each shift has a clear scope and isn’t dependent on unfinished work from the previous team.
That’s my concern. We looked at split shifts, but I worry that crew handover issues will just cause more delays. Would shift-based work zones be a better solution?
We use cookies to enhance your browsing experience, serve personalized ads or content, and analyze our traffic. By clicking "Accept All", you consent to our use of cookies. Read our Cookie Policy to learn more.
(Contracts & Claims Consultant): If the client won’t allow schedule extensions, are they at least acknowledging the inefficiencies caused by stacking? Some subs might have a valid claim for productivity losses if they’re forced into a rushed schedule.